Related articles
Inspection available to Authentic Buyers.
(Was a carbide manufacturing unit, established by British Gov)
Factory on Government Land about 11 ½ Acres Land leased from the earlier Travancore Government.
Reason for Closure: High electric charges
Period of Closure: more than 10 Years
Claims and Litigation
1. Labor Claims: All settled, few labors are still occupying the quarters in the premises. The confirmation from Labor Commissioner available
2. Electricity : The KSEB liability one time settled liability of Rs.4.5 Cr is standing which will be cleared once buyer makes the deposit
Kerala Government has offered the support to clear the land. The Government wants to develop the 11 ½ acres land into IT Park. All necessary assistance will be provided from Government to clear the land.
Plant Details:
1. The plant is adjoining to main Raod (MC road)
2. The plant is fully constructed on structural beams
3. Includes Electric furnace, electric installations and other machineries
4. All structural beams are founded with steel foundations
5. No side masonry walls for the main plant building
Vehicles (12 Nos)
1. Eicher Trucks
2. One Ceilo Car
Scrap Details
1. M.S. Scrap : 55000 MT
2. Gear Boxes : 150 MT
3. Machineries : 800 MT
4. Cranes : 5 Nos
5. Electric Control Panels : 30 Nos
6. Cables of Various Sizes : 5000 M
7. Copper : 1200 MT
8. Aluminum : 800 MT
9. Brass : 40 MT
10. Welding Set : 5 Nos
11. Weigh Bridge : 2 Nos
12. Nitrogen Plant : 1 Nos
13. Rails : 15 MT
14. Bucket Conveyor : 70 M
15. Conveyor : 200 M
16. Vehicles : 12 Nos
17. Asbestos Sheets : 50 Loads
Estimated Quantity at the time of Closure: 70,000 MT and above
Besides above there are 2 stores with various imported and indigenous spares and other part, stocked before closure of the factory.
EXPECTED COST OF FACTORY: Plz Contact
Payment Terms
1. First Step Advance at the time of signing the contract: Rs. 30 Cr.
2. Balance payment in 2 steps with 45 days of dismantling
CUTTING AND DISMANTLING
1. Daily dismantling minimum 200MT
2. Workers required 30 Nos
3. Total period of Dismantling 300 days approx
4. JCB in 2 Nos and Winches in 2 Nos required
5. Gas Cutter and other cutting equipments required
Approx cost of cutting and removing: Rs. 8 per Kg
Loading Charges to be paid to Local Union
Related articles
- CII to set up Centre for Excellence in Kerala (news.in.msn.com)
- Stop Kerala's Siruvani schemes: Jayalalithaa (thehindu.com)
- Row over KSEB tower resolved (thehindu.com)
- KSEB suspends work on crucial line again (thehindu.com)
- Kerala: An Effective Model of Local Self Governance (shantitda.wordpress.com)
- Kovalam - On the Beach Front - Bangalore, India (travelpod.com)
- For the Entrepreneur in You (fwdlife.in)
- India's Bribe Analysis: Rs. 1766595 Bribe paid in 15 days (indologygoa.wordpress.com)
- Kerala (slideshare.net)
- Another war for water begins between Tamil Nadu and Kerala (ndtv.com)